Invitation for Contract Awards Detail
GOVERNMENT OF THE PEOPLE'S REPUBLIC OF BANGLADESH
Ministry/Division |
: |
Ministry of Home Affairs |
Agency |
: |
Bangladesh Coast Guard Force |
Procuring Entity Name |
: |
Project Director |
Procuring Entity Code |
: |
|
Procuring Entity District |
: |
Dhaka |
Contract Award for |
: |
Works |
Invitation/Proposal Reference No |
: |
44.08.2680.030.20.031.22.74 dated 27 April 2022. |
KEY INFORMATION
|
Procurement Method |
: |
NCT |
Tendering Method |
: |
One Stage & Two envelope Tendering Method |
FUNDING INFORMATION
|
Budget and Source of Funds |
: |
Development Budget GOB |
Development Partner (if applicable) |
: |
NA |
PARTICULAR INFORMATION
|
Project/Programme Name (if applicable) |
: |
|
Tender/Proposal Package No |
: |
WD-10 |
Tender/Proposal Package Name |
: |
Construction of Slipways including Winch house, Sheave block, Dolphin Jetty, Tower crane lane, Cradle, Retaining wall, Pavement and Temporary cofferdam and Dredging work at Gazaria, Munshigonj. |
Date of Advertisement |
: |
30/04/2022 |
Date of Notification of Award |
: |
05/09/2022 |
Date of Contract Signing |
: |
21/09/2022 |
Proposed Date of Contract Completion |
: |
18 months after signing contract |
No. of Tenders/Proposals Sold |
: |
4 |
No. of Tenders/Proposals Received |
: |
2 |
No. of Tenders/Proposals Responsive |
: |
1 |
INFORMATION ON AWARD
|
Brief Description of Contract |
: |
With the prior approval of annual procurement plan for the financial year 2021-2022 - The procurement of Slipway and related accessories (Package: WD-10) under the project titled “Establishment of Logistics and Fleet Maintenance Facilities for Bangladesh Coast Guard”. On behalf a tender notice (One stage two envelop) was published on 30th April 2022 in a widely circulated English newspaper “Our Time” and a Bengali newspaper “Daily Kaler Kantha”. In view of above total 04 in no companies purchased the tender documents within the stipulated period mentioned in the tenders and out of them 02 in no companies submitted their tender documents. Then submitted tender documents were Evaluated by the detailed Tender Evaluation Committee (TOC) and found NS Construction –ML (JV) as responsive according to the Public Procurement Rules 2008. |
Contract Value |
: |
999487133.76 |
Name of Supplier/Contractor/Consultant |
: |
NS Construction-ML (JV) |
Location of Supplier/Contractor/Consultant |
: |
Office-1 N S Construction. House-3, Road-28, Block-k, Banani-1213, Dhaka, Bangladesh Office-2 Mayar Limited, Brisa De Silvestra, Level- A-8, Road-04, House-31, Block-F, Banani, Dhaka-1213, Bangladesh |
Location of Delivery/Works/Consultancy |
: |
Munshiganj |
Is the Contract Signed with the same person stated in the NOA |
: |
Yes |
If No give reason why |
: |
|
Was the Performance Security provided in due time? |
: |
Yes |
If No give reason why |
: |
|
Was the Contract Singed in due time? |
: |
Yes |
If No give reason why |
: |
|
ENTITY DETAILS
|
Name of Authorised Officer |
: |
Captain Mahbub Hasan |
Designation of Authorised Officer |
: |
Project Director |