Contract Award for |
: |
Works |
Invitation/Proposal Reference No |
: |
EE/CTG/DPHE-256, 25-02- 2020 |
KEY INFORMATION
|
Procurement Method |
: |
NCT |
Tendering Method |
: |
Open Tendering Method |
FUNDING INFORMATION
|
Budget and Source of Funds |
: |
Development Budget Grant/Credit |
Development Partner (if applicable) |
: |
International Development Association(IDA), Asian Infrastructure Investment Bank (AIIB) |
PARTICULAR INFORMATION
|
Project/Programme Name (if applicable) |
: |
|
Tender/Proposal Package No |
: |
BMWSSP/WD-12 |
Tender/Proposal Package Name |
: |
Construction of Piped Water Supply Scheme at Banskhali and Chandanaish Pourashavas |
Date of Advertisement |
: |
25/02/2020 |
Date of Notification of Award |
: |
21/10/2020 |
Date of Contract Signing |
: |
04/11/2020 |
Proposed Date of Contract Completion |
: |
04/05/2022 |
No. of Tenders/Proposals Sold |
: |
2 |
No. of Tenders/Proposals Received |
: |
2 |
No. of Tenders/Proposals Responsive |
: |
1 |
INFORMATION ON AWARD
|
Brief Description of Contract |
: |
Installation of Intake Jetty, Production well, Pump house, submersible water pump, transmission pipe line, office building, treatment plant, electrical works, overhead tanks, boundary wall and site development, environmental mitigation works, trial run of the whole scheme etc. |
Contract Value |
: |
412174298.407 |
Name of Supplier/Contractor/Consultant |
: |
ABM Water Company Limited |
Location of Supplier/Contractor/Consultant |
: |
Mubarak Tower, Laldighirpar, Ground Floor, Sylhet |
Location of Delivery/Works/Consultancy |
: |
Chattogram |
Is the Contract Signed with the same person stated in the NOA |
: |
Yes |
If No give reason why |
: |
|
Was the Performance Security provided in due time? |
: |
Yes |
If No give reason why |
: |
|
Was the Contract Singed in due time? |
: |
Yes |
If No give reason why |
: |
|
ENTITY DETAILS
|
Name of Authorised Officer |
: |
Suman Roy |
Designation of Authorised Officer |
: |
Executive Engineer |