Invitation for Contract Awards Detail
GOVERNMENT OF THE PEOPLE'S REPUBLIC OF BANGLADESH
Ministry/Division |
: |
Ministry of Local Government, Rural Development and Co-operatives |
Agency |
: |
Kotalipara Pourashava |
Procuring Entity Name |
: |
H.M Ohidul Islam , Mayor, Kotalipara Pourashava, Kotalipara, Gopalganj |
Procuring Entity Code |
: |
|
Procuring Entity District |
: |
Gopalganj |
Contract Award for |
: |
Works |
Invitation/Proposal Reference No |
: |
Kot/pour/Dev/2017/162,Date-14/09/2017 |
KEY INFORMATION
|
Procurement Method |
: |
NCT |
Tendering Method |
: |
Open Tendering Method |
FUNDING INFORMATION
|
Budget and Source of Funds |
: |
Development Budget GOB |
Development Partner (if applicable) |
: |
|
PARTICULAR INFORMATION
|
Project/Programme Name (if applicable) |
: |
|
Tender/Proposal Package No |
: |
KOTA/POUR/PBH.VE/2017-18/01 |
Tender/Proposal Package Name |
: |
Construction of Vertical Extension of Kotalipara Pourashava Office Bhaban under Kotalipara Pourashava F/Y -2017-18 |
Date of Advertisement |
: |
14/09/2017 |
Date of Notification of Award |
: |
15/03/2018 |
Date of Contract Signing |
: |
11/04/2018 |
Proposed Date of Contract Completion |
: |
270 Days |
No. of Tenders/Proposals Sold |
: |
77 |
No. of Tenders/Proposals Received |
: |
7 |
No. of Tenders/Proposals Responsive |
: |
5 |
INFORMATION ON AWARD
|
Brief Description of Contract |
: |
Construction of Vertical Extension of Kotalipara Pourashava Office Bhaban under Kotalipara Pourashava F/Y -2017-18
|
Contract Value |
: |
TK-1,07,98,152.804 ( Taka One Crore Seven Lac Ninety Seven Thousand One Hundred Fifty Two & Paisa Eight zero Four ) only |
Name of Supplier/Contractor/Consultant |
: |
.Mazid Sons Construction Limited, House No -288, New DOHS, Mohakhali, Dhaka-1206
|
Location of Supplier/Contractor/Consultant |
: |
House No -288, New DOHS, Mohakhali, Dhaka-1206
|
Location of Delivery/Works/Consultancy |
: |
Gopalganj |
Is the Contract Signed with the same person stated in the NOA |
: |
No |
If No give reason why |
: |
|
Was the Performance Security provided in due time? |
: |
No |
If No give reason why |
: |
|
Was the Contract Singed in due time? |
: |
No |
If No give reason why |
: |
|
ENTITY DETAILS
|
Name of Authorised Officer |
: |
Sarder Mahbubur Rahman |
Designation of Authorised Officer |
: |
Executive Engineer, Kotalipara Pourashava, Gopalgang
|