Invitation for Contract Awards Detail
GOVERNMENT OF THE PEOPLE'S REPUBLIC OF BANGLADESH
| Ministry/Division |
: |
Ministry of Energy, Power and Minearal Resources |
| Agency |
: |
Northern Electricity Supply Company Ltd. |
| Procuring Entity Name |
: |
Project Director, Extension and Renovation Project of Distribution Line & Sub-station of Rangpur Division, NESCO, Bangladesh |
| Procuring Entity Code |
: |
|
| Procuring Entity District |
: |
Rangpur |
| Contract Award for |
: |
Goods |
| Invitation/Proposal Reference No |
: |
Contract No: 27.29.0000.015.07.274.2023-3337; Date: 13/09/2023 |
KEY INFORMATION
|
| Procurement Method |
: |
ICT |
| Tendering Method |
: |
One Stage & Two envelope Tendering Method |
FUNDING INFORMATION
|
| Budget and Source of Funds |
: |
Development Budget GOB |
| Development Partner (if applicable) |
: |
|
PARTICULAR INFORMATION
|
| Project/Programme Name (if applicable) |
: |
|
| Tender/Proposal Package No |
: |
Package-1, Lot-1 |
| Tender/Proposal Package Name |
: |
Design, Supply, Erection, Installation, Testing and Commissioning of Upgradation of Katkipara, Mahigonj, Dhanghora & Niamotpur 33/11 KV Substation on Turnkey Basis (ICT) (RDPP Package-01, Lot-1) |
| Date of Advertisement |
: |
21/03/2023 |
| Date of Notification of Award |
: |
16/08/2023 |
| Date of Contract Signing |
: |
13/09/2023 |
| Proposed Date of Contract Completion |
: |
13/09/2024 |
| No. of Tenders/Proposals Sold |
: |
7 |
| No. of Tenders/Proposals Received |
: |
3 |
| No. of Tenders/Proposals Responsive |
: |
3 |
INFORMATION ON AWARD
|
| Brief Description of Contract |
: |
|
| Contract Value |
: |
USD 3,113,429.00 (THREE MILLION ONE HUNDRED THIRTEEN THOUSAND FOUR HUNDRED TWENTY-NINE DOLLARS) + BDT 2,48,82,095.00 (TWO CRORE FORTY-EIGHT LAKH EIGHTY-TWO THOUSAND AND NINETY-FIVE) |
| Name of Supplier/Contractor/Consultant |
: |
JV of China United Engineering Corporation Ltd. & JRC Powertech |
| Location of Supplier/Contractor/Consultant |
: |
27/1, Rajabari, Genda, Savar, Dhaka |
| Location of Delivery/Works/Consultancy |
: |
Dhaka |
| Is the Contract Signed with the same person stated in the NOA |
: |
Yes |
| If No give reason why |
: |
|
| Was the Performance Security provided in due time? |
: |
Yes |
| If No give reason why |
: |
|
| Was the Contract Singed in due time? |
: |
Yes |
| If No give reason why |
: |
|
ENTITY DETAILS
|
| Name of Authorised Officer |
: |
D.M. Abu Hena Mostafa Kamal |
| Designation of Authorised Officer |
: |
Project Director |