Invitation for Contract Awards Detail
GOVERNMENT OF THE PEOPLE'S REPUBLIC OF BANGLADESH
Ministry/Division |
: |
Ministry of Water Resources |
Agency |
: |
Bangladesh Water Development Board (BWDB) |
Procuring Entity Name |
: |
Project Director, CEIP-1, BWDB, Dhaka |
Procuring Entity Code |
: |
|
Procuring Entity District |
: |
Dhaka |
Contract Award for |
: |
Services |
Invitation/Proposal Reference No |
: |
CEIP-1/S1-C/1007 Dated 8-11-2017 |
KEY INFORMATION
|
Procurement Method |
: |
NCT |
Tendering Method |
: |
Selection based on Consultants’ Qualification (SCQ) |
FUNDING INFORMATION
|
Budget and Source of Funds |
: |
Development Budget Grant/Credit |
Development Partner (if applicable) |
: |
IDA ( World Bank) |
PARTICULAR INFORMATION
|
Project/Programme Name (if applicable) |
: |
|
Tender/Proposal Package No |
: |
CEIP-1/A2 & B1/ S1-C |
Tender/Proposal Package Name |
: |
Non-Governmental Organization (NGO) Services to implement (a) Social Mobilization with Social Action Plan (incl. setting up WMOs); (b) Social afforestation and (c) Implementation of Integrated Pest Management (IPM) Plan for Polder No.39/2C |
Date of Advertisement |
: |
08/11/2017 |
Date of Notification of Award |
: |
17/02/2019 |
Date of Contract Signing |
: |
25/02/2019 |
Proposed Date of Contract Completion |
: |
30 June 2020 |
No. of Tenders/Proposals Sold |
: |
6 |
No. of Tenders/Proposals Received |
: |
3 |
No. of Tenders/Proposals Responsive |
: |
2 |
INFORMATION ON AWARD
|
Brief Description of Contract |
: |
The objectives of the consulting services are to manage and oversee tasks for social mobilization, participatory scheme cycle management(PSM) and participatory afforestation in relation to the successful implementation of the CEIP-I. Specifically, consulting services was sought for (a) Social mobilization including setting up WMOs for introduction of IWRM practices through preparation and implementation of Social Action plan through engagement of local communities and community groups for PSM and participatory O&M of schemes, (b) Implementation of afforestation program in the fore-shore areas and Embankment Slope with ecologically appropriate species by adopting social afforestation approach, and (c) Implementation of the IPM practices for Polder No.39/2C in Pirojpur District under Coastal Embankment Improvement Project, Phase-1, (CEIP-1) |
Contract Value |
: |
BDT 29,871,825.00 |
Name of Supplier/Contractor/Consultant |
: |
JV of RIC ( Resources Integration Centre) and Swabalambi Samaj Unnayan Sangstha (SSUS) |
Location of Supplier/Contractor/Consultant |
: |
House # 20, Road No.11 (New), 32 (Old), Dhanmondi R/A,
Dhaka, Bangladesh
|
Location of Delivery/Works/Consultancy |
: |
Pirojpur |
Is the Contract Signed with the same person stated in the NOA |
: |
Yes |
If No give reason why |
: |
|
Was the Contract Singed in due time? |
: |
Yes |
If No give reason why |
: |
|
ENTITY DETAILS
|
Name of Authorised Officer |
: |
Md. Habibur Rahman |
Designation of Authorised Officer |
: |
Chief Engineer and Project Director,
CEIP-1, BWDB, Dhaka, Bangladesh |